PMP Question of the Week: Time Estimates

pmpweek06You have received maximum, minimum and most-likely time estimates from your team for activities to be done on the project. Which time estimate should you use when developing your project schedule?

A. Most-likely
B. Max
C. Three-point estimate
D. (Max – Min)