PMP Question of the Week: EAC Calculation

pmpweek02You want to determine the most accurate Estimate at Completion (EAC) calculation, regardless of project performance. Which formula should you use?

A. EAC = BAC ÷ SPI
B. EAC = BAC + AC + EV
C. EAC = AC + EV
D. EAC = AC + bottom-up ETC

Reveal Answer