You are the project manager on a very large, complex system software deployment project. The schedule is set for three years and the budget is $8 million. The project is approximately 50% complete but is slightly behind schedule and over budget (SPI = 0.94 and CPI = 0.96). One of the key project stakeholders (accounting department functional manager) contacts you to discuss what the accounting departmental manager believes to be required additional scope. You ask this key stakeholder to put his request in the form of a Change Order Request (COR). When you receive the COR, you expect to work the COR through the Control Scope process. After the impact of the COR has been determined, what is the best thing to do next?
A. Complete the Perform Integrated Change Control process.
B. Discuss with the project sponsor why this requested scope increase was not included in the original project charter/plan.
C. Query all stakeholders to ensure that there are not more potential scope changes being discussed or considered.
D. Make sure the real impact on the project of this COR is fully understood by all stakeholders.
Related Resources
PMP Exam Prep Mobile App
Project Management White Papers
Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program
PMP Exam Prep Question of the Week Series
- PMP Question of the Week: Perform Quality Assurance
- PMP Question of the Week: Quantitative Data
- PMP Question of the Week: Situational Continuum Leadership
- PMP Question of the Week: Stakeholder Register
- PMP Question of the Week: Plan Risk Responses
- PMP Question of the Week: Performance Improvement
- PMP Question of the Week: Budgets
- PMP Question of the Week: EAC
- PMP Question of the Week: Quality Control Techniques
- PMP Question of the Week: Outlining Project Roles
- PMP Question of the Week: Engage Stakeholders
- PMP Question of the Week: Breakdown Structures
- PMP Question of the Week: Quality Management
- PMP Question of the Week: Decision Tree
- PMP Question of the Week: CV
- PMP Question of the Week: Critical Path
- PMP Question of the Week: Project Cost Management
- PMP Question of the Week: Change Request
- PMP Question of the Week: Contract Complete
- PMP Question of the Week: Control Procurements
- PMP Question of the Week: Control Risks
- PMP Question of the Week: Change Requests
- PMP Question of the Week: Plan Communications Management
- PMP Question of the Week: Stakeholder Concerns
- PMP Question of the Week: Effective Communication
- PMP Question of the Week: Project Review
- PMP Question of the Week: Task Duration Predecessor
- PMP Question of the Week: Risk Impacts
- PMP Question of the Week: Change Order Request Next Steps
