PMPFormulaOTW475166460An S-curve for your project’s PV, EV and AC show AC above PV and EV below PV. What does this indicate?

A. On budget and on schedule.
B. On budget but behind schedule.
C. Over budget but on schedule.
D. Over budget and behind schedule.