PMP Exam Prep Question of the Week

pmpweek03

During the Executing and the Monitoring and Controlling phases, the project sponsor tells you, the project manager, that the requirements have changed for one of the project deliverables. Based on this new knowledge, you have to complete additional planning. What is the term used to describe this series of events?

  1. Regression testing
  2. Progressive planning
  3. Progressive elaboration
  4. Project elaboration

The correct answer is 3.

Regression testing has nothing to do with this question. Progressive planning and project elaboration may sound correct, but they are not applicable in this situation.

Related Resources
PMP Mobile App

Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program

Please support our Sponsors here :