PMP Exam Prep Question of the Week

Which of the following processes do not benefit from the outputs of the Develop Schedule process?

  1. Control schedule
  2. Estimate costs
  3. Determine budget
  4. Form team

The correct answer is 4.

The project schedule becomes an input to controlling the schedule, estimating costs, and determining the budget. Team formation is not a recognized process.