PMP Exam Prep Question of the Week

pmpweek07Lessons-learned documentation, written notice that the contract has been completed, and the compilation of the procurement file occur during which process?

  1. Control Procurements
  2. Close Procurements
  3. Plan Procurement Management
  4. Conduct Procurements

The correct answer is 2.

The outputs of Close Procurements are closed procurements and organizational process assets updates. The procurement file and lessons learned documentation are among the organizational process assets that are updated as a part of Close Procurements.