PMP Exam Prep Question of the Week

A major construction company is building a high-rise office building in which the offices on each floor are almost identical in layout and size. Which of the following tools and techniques would the project manager find most helpful in developing the work schedule for this construction project?

  1. Historical information from similar projects
  2. A network diagram
  3. Schedule network templates
  4. Expert judgment

The correct answer is 3.

Schedule network templates can be reused to develop the network diagrams for projects that are similar to past projects. They are a subset of the network diagram and are based on historical information from similar, past projects. Historical information, a network diagram, and expert judgement are also correct but Schedule network templates is the best, most comprehensive answer.

Related Resources
PMP Mobile App

Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program

Please support our Sponsors here :