 Which of the following processes do not benefit from the outputs of the Develop Schedule process?
Which of the following processes do not benefit from the outputs of the Develop Schedule process?
- Control schedule
- Estimate costs
- Determine budget
- Form team
The correct answer is 4.
The project schedule becomes an input to controlling the schedule, estimating costs, and determining the budget. Team formation is not a recognized process.
Related Resources
PMP Mobile App
Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program
PMP Weekly Question Series
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
Please support our Sponsors here :  
		
	