PMP Exam Prep Question of the Week

A project team has worked long and hard on a complex procurement statement of work for a significant purchase. After much work and many reviews, all have agreed that the procurement statement of work is complete. But, you, the project manager, still have some concerns about if it addresses all of the project needs in sufficient detail to avoid contract disputes later. You ask a peer for advice on what to do during the upcoming bidder conference. The best advice the peer can give includes:

Read more