PMP Exam Prep Question of the Week

pmpweek02

Your team is in the middle of executing a project that is now projected to run three weeks too long. Which of the following adjustments would allow the project to be delivered on time?

  1. Substitute a lesser experienced programmer for a more experienced one.
  2. Move resources from a noncritical task to a critical path task.
  3. Modify the purchase of new equipment to less expensive equipment.
  4. Allow a tester on the project to temporarily work on another, more critical project.

The correct answer is 2.

Answers 1 and 4 would likely result in adding additional time to the project; 3 would contribute to cost savings, but does not necessarily have an impact on time.

Related Resources
PMP Mobile App

Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program

Please support our Sponsors here :