PMP Exam Prep Question of the Week

pmpweek05Which of the following is not a process you will complete during Project Cost Management?

  1. Estimate costs
  2. Determine budget
  3. Control costs
  4. Determine critical path

The correct answer is 4.

Determining the critical path is a Project Time Management process. Answers 1, 2 and 3 are all processes of Project Cost Management.

Related Resources
PMP Exam Prep Mobile App

Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program

Please support our Sponsors here :